I need a gas meter raised off the floor so i can fit a cuboard unit about 7 inch`s.. and needs recconecting to the gas cooker pipe ..
Could upload a picture of the meter if needed...
I need a gas meter raised off the floor so i can fit a cuboard unit about 7 inch`s.. and needs recconecting to the gas cooker pipe ..
Could upload a picture of the meter if needed...
I think you need to speak to Transco about moving meters m8, im sure pipework on the inlet side of the meter is Transco's responsibility.
TIM-MAY!!!
SouthPark
Thanks for your reply Roty
The meter has a flexable pipe fitted from the main supply..
just need it raising as high as the flexable pipe will allow then reconnecting
back to the outlet pipe..
When I had out gas meter moved whilst building our extension a friendly Transco guy did it for £60 Saved an awful lot of paperwork.
Job done thank`s guys